Wednesday, November 2, 2011

Revised Calendar - Nov.3

November 3rd - have list of potential voice actors

8th - have demo reels completed & finished revising resume, sketch two more backgrounds (8/10 total)
10th - Have all main characters completed, and begin basic loop animations
15th - Begin basic loop animation, revised demo reels, have all backgrounds sketched
17th - Continue loop animation
22nd - Have all assets done, Begin main animation
24th Thanksgiving Break- Thanksgiving (Not working on Senior Studio today...)
29th - continue animation

December 1st - Confirm & start recording voices
6th - continue animation
8th - demo reels finished, and resume finished, have DVD portfolio ready

Winter Break - Hand Paint All Background Panels

January 17th - Have organized presentation to show on first/second day.
19th - continue animation, begin drafting cover letters
24th - continue animation
26th - continue animation
31st - continue animation

February 2nd - continue animation
7th - Finish animation
9th - Finish Coloring any uncolored assets, Rerecord voices to animation
14th - Begin animation revision animation revision, begin sending out for job positions
16th - continue animation revision, add revised voices to animation
21st - continue animation revision, and begin adding any effects deemed necessary
23rd - continue animation revision and cleaning, continue effects
28th - continue animation and cleaning, finish effects

March 1st - Record sound, continue animation cleaning
6th - Begin sound mixing, continue animation cleaning
8th - Mix sound, finish animation cleaning
13th - Mix sound
15th - Mix sound
20th - Finished Product - Draft
22nd - 1st Revision - Finished Product
27th - 2nd Revision Finished Product
29th - Finished animation, be ready to turn in.

No comments: